Megasolar

Mega-solar projects

vntkg solar

vntkg’s efforts

vntkg endeavors contribution to the environment by promoting mega solar project all over the country.
We manage and install mega solar project all over the country after installing solar panels
on the rooftop pf our logistics storage in Kaga, Ishikawa.
Currently, we have 40MW output for total which contributes to the reduction of CO2 more than 10000t every year.
We try to promote use of renewable energy, contribute to region, and protect environment from now on.

List of locating place

Hokkaido/Tohoku region

University of Tohokufukushi, Okura power plant
  • Expected electric power generationApproximately 1,988,938kwh(Standard home: About 350 households)
  • Reduction in CO2Approximately 630t(Plantation: approximately 45,000 Japanese cedars)
  • Reduction in oilApproximately 450t(Approximately 2,300drums)
InterconnectionSep-13
AddressIttupongi Aoba-ku Sendai-city, Miyagi
Installed siteIdle land owned by university
PanelGRID Polycrystalline (230W)
Total: 1,803kw
Max output1,500kw
Annual expected electric power generationApproximately 1,988,938kwh

Kanto region

vntkg solar Kasama No1. power plant
  • Expected electric power generationApproximately 2,630,211kwh(Standard home: About 350 households)
  • Reduction in CO2Approximately 830t(Plantation: approximately 45,000 Japanese cedars)
  • Reduction in oilApproximately 600t(Approximately 3,000drums)
InterconnectionSep-15
AddressTaira-cho Sakama-city, Ibaraki
Installed siteIdle land
PanelHanwha Polycrystalline(255W)
Total: 2,399kw
Max output1,990kw
Annual expected electric power generationApproximately 2,630,211kwh
vntkg,solar Kasama No.2 power plant
  • Expected electric power generationApproximately 2,630,211kwh(Standard home: About 350 households)
  • Reduction in CO2Approximately 830t(Plantation: approximately 45,000 Japanese cedars)
  • Reduction in oilApproximately 600t(Approximately 3,000drums)
InterconnectionSep-15
AddressTaira-cho Sakama-city, Ibaraki
Installed siteIdle land
PanelHanwha Polycrystalline(255W)
Total: 2,399kw
Max output1,990kw
Annual expected electric power generationApproximately 2,630,211kwh
vntkg solar Kamitakane power plant
  • Expected electric power generation約2,559,888kwh(Standard house: About 450 households)
  • Reduction in CO2Approximately 810t(Plantation: approximately 58,000 Japanese cedars)
  • Reduction in oilApproximately 580t(Approximately 2,900drumns)
InterconnectionDec-15
AddressKamitakane Ichihara-city, Chiba
Installed siteIdle land
PanelHanwha Polycrystalline(260W)
Total:2,400kw
Max output1,990kw
Annual expected electric power generationApproximately 2,559,888kwh
vntkg solar Takasaki power plant
  • Expected electric power generationApproximately 2,851,322kwh(Standard home: About 510 households)
  • Reduction in CO2Approximately 900t(Plantation: approximately 64,000 Japanese cedars)
  • Reduction in oilApproximately 650t(Approximately 3,200drums)
InterconnectionJun-16
AddressSumomogatakehara Kurabuchimachigonda Takasaki-city, Gunma
Installed siteIdle land
PanelIwatec Polycrystalline(265W)
Total: 2,374kw
Max output1,990kw
Annual expected electric power generationApproximately 2,851,322kwh

Hokuriku/Chubu region

vntkg solar Kaga power plant
  • Expected electric power generationApproximately 1,400,133kwh(Standard house: About 250 households)
  • Reduction in CO2Approximately 440t(Plantation: approximately 31,000Japanese cedars)
  • Reduction in oilApproximately 320t(Approximately 1,600drums)
InterconnectionApr-13
AddressMisaki-cho Kaga-city, Ishikawa
Installed siteRooftop of storage
PanelGRID Polycrystalline (182W-230W)
Total: 1,485kw
Max output1,454.2kw
Annual expected electric power generationApproximately 1,400,133kwh
vntkg solar: Akiha power plant
  • Expected electric power generationApproximately 2,211,030kwh(Standard house: approximately 390 households)
  • Reduction in CO2Approximately 700t(Plantation: approximately 50,000Japanese cedars)
  • Reduction in oilApproximately 500t(Approximately 2,500drums)
InterconnectionApr-15
AddressGawagasawa Akiha-ku Nigata-city, Nigata
Installed siteIdle land
PanelHanwha Polycrystalline(255W)
Total: 2,777kw
Max output1,990kw
Annual expected electric power generationApproximitely2,211,030kwh
vntkg solar: Kahoku power plant
  • Expected electric power generationApproximately 2,454,467kwh(Standard house: Approximately 430 households)
  • Reduction in CO2Approximately 770tPlantation: approximately 50,000Japanese cedars
  • Reduction in oilApproximately 560tApproximately 2,800 drums
InterconnectionApr-15
AddressNumai Kahoku-city, Ishikawa
Installed siteIdle land
PanelHanwha Polycrystalline(255W)
Total: 2,436kw
Max output1,990kw
Annual expected electric power generationApproximately 2,454,467kwh
vntkg solar: Tamadate power plant
  • Expected electric power generationApproximately 2,622,768kwh(Standard house: Approximately 460 households)
  • Reduction in CO2Approximately 830t(Plantation: approximately 59,000Japanese cedars)
  • Reduction in oilApproximately 600t(Approximately 3,000 drums)
InterconnectionSep-15
AddressShimizu-cho Tamadate Hakuigun, Ishikawa
Installed siteIdle land
PanelHanwha Polycrystalline(260W)
Total: 2,424kw
Max output1,990kw
Annual expected electric power generationApproximately 2,622,768kwh

Kinki region

vntkg solar Meiwacho No1 power plant
  • Expected electric power generationApproximately 2,943,395kwh(Standard house: Approximately 520 households)
  • Reduction in CO2Approximately 930t(Plantation: approximately 66,000 Japanese cedars)
  • Reduction in oilReduction in oil(Approximately 3,300 drums)
InterconnectionSep-14
AddressShowacho takigun, Miwa
Installed siteIdle land
PanelJINKO Polycrystalline(255W)
Total: 2,570kw
Max output1,990kw
Annual expected electric power generationApproximately 2,943,395kwh
vntkg solar Meiwacho No2. power plant
  • Expected electric power generationApproximately 2,747,551kwh(Standard house: Approximately 490 household)
  • Reduction in CO2Approximately 860t(Plantation: Approximately 62,000 Japanese cedars)
  • Reduction in oilApproximately 620t(Approximately 3,100drums)
InterconnectionSep-14
AddressTowaco takigun, Miwa
Installed siteIdle land
PanelJINKO Polycrystalline(255W)
Total: 2,399kw
Max output1,990kw
Annual expected electric power generationApproximately 2,747,551kwh
vntkg solar Nagahama power plant
  • Expected electric power generationApproximately 1,886,415kwh(Standard house: Approximately 330 houses)
  • Reduction in CO2Approximately 590t(Plantation: Approximately 42,000 Japanese Cedars)
  • Reduction in oilApproximately 430t(Approximately 2,100 drums)
InterconnectionMar-15
AddressYogocho Nagahama-city, Shigaken
Installed siteIdle land
PanelApollo Monocrystalline (305W)
Total: 1,793kw
Max output1,500kw
Annual expected electric power generationApproximately 1,886,415

Kyusyu region

vntkg solar Kawasaki-cho power plant
  • Expected electric power generationApproximately 1,862,080kwh(Standard house: Approximately 330 houses)
  • Reduction in CO2Approximately 590t(Plantation: Approximately 42,000 Japanese cedars)
  • Reduction in oilApproximately 420t(Approximately 2,100drums)
InterconnectionApr-13
AddressTahara kawasaki-cho tagawa-gun, Fukuoka
Installed sitetown-owned land
PanelGRID Polycrystalline (182W)
Hanwha Polycrystalline (260W)
Total: 1,784kw
Max output1,490kw
Annual expected electric power generationApproximately 1,862,080kwh
vntkg solar Meiseizi power plant
  • Expected electric power generationApproximately 2,731,528kwh(Standard house: Approximately 480 households)
  • Reduction in CO2Approximately 860t(Plantation: Approximately 61,000 Japanese cedars)
  • Reduction in oilApproximately 620t(Approximately 3,100drums)
InterconnectionJan-14
AddressMeseiji Izuka city, Fukuoka
Installed siteIdle land
PanelGRID Polycrystalline (182W・263W)
Total: 2,453kw
Max output1,990kw
Annual expected electric power generationApproximately 2,731,528kwh
vntkg soar Kaharamachi power plant
  • Expected electric power generationApproximately 1,795,647kwh(Standard house: Approximately 320 households)
  • Reduction in CO2Approximately 560t(Plantation: Approximately 40,000 Japanese cedars)
  • Reduction in oilApproximately 410t(Approximately 2,000 drums)
InterconnectionNov-14
AddressKaharumachi Tagawa-gun, Fukuoka
Installed siteTown-owned land/Idle land
PanelHanwah Polycrystalline (250W)
Total: 554kw
Max output1,490kw
Annual expected electric power generationApproximately 1,795,647kwh
vntkg solar Kikuchi power
  • Expected electric power generationApproximately 2,393,724kwh(Standard house: Approximately 420 households)
  • Reduction in CO2Approximately 750t(Plantation: Approximately 54,000 Japanese cedars)
  • Reduction in oilApproximately 540t(Approximately 2,700 drums)
InterconnectionJun-15
AddressKyokushibenri Kikuchi-city, Kumamoto
Installed siteIdle land
PanelHanwah Polycrystalline (255W)
Total: 2,064kw
Max output1,990kw
Annual expected electric power generationApproximately 2,393,724kwh
vntkg solar Koshi power plant
  • Expected electric power generationApproximately 2,006,229kwh(Standard house: Approximately 360 households)
  • Reduction in CO2Approximately 630t(Plantation: Approximately 45,000 Japanese cedars)
  • Reduction in oilApproximately 460t(Approximately 2,300drums)
InterconnectionDec-15
AddressTakabagohonmatsu, Koshi-city, Kumamoto
Installed siteIdle land
PanelHanwah Polycrystalline (260W)
Approximately 731kw
Max output1,490kw
Annual expected electric power generationApproximately 2,006,229kwh